The PM Surya Ghar Central Government Subsidy Scheme Explained
Under the national PM Surya Ghar: Muft Bijli Yojana, the Ministry of New and Renewable Energy (MNRE) provides Direct Benefit Transfer (DBT) subsidies directly into the bank accounts of Kerala homeowners installing grid-connected rooftop solar.
Subsidy Slab Breakdown
- 1 kW System: ₹33,000 Central DBT Subsidy
- 2 kW System: ₹66,000 Central DBT Subsidy
- 3 kW to 10 kW Systems: ₹78,000 Maximum Central DBT Subsidy
Step-by-Step Application Process in Kerala
- National Portal Registration: Register on pmsuryaghar.gov.in using your electricity consumer number from your KSEB bill and Aadhaar-linked mobile number.
- Technical Feasibility Approval (TFR): KSEB electrical section verifies transformer capacity and issues technical feasibility approval (typically 7–10 working days).
- Installation by MNRE Registered EPC: Green Ray Solutions executes turnkey installation using DCR (Domestic Content Requirement) certified Tier-1 panels and smart on-grid inverters.
- KSEB Joint Inspection & Net Meter Synchronization: KSEB sub-engineer inspects earthing, SPDs, and installs the bi-directional meter.
- Direct Bank Release: Following meter commissioning, the ₹78,000 DBT subsidy is transferred directly to your bank account within 30–45 days.